THE NATIONAL GRID ELECTRICITY TRANSMISSION PLC (LONDON POWER TUNNELS 2) (CIRCUIT 2 - NEW CROSS TO HURST) COMPULSORY PURCHASE ORDER 2019 Compulsory Purchase of Land and New Rights in Land at New Cross to Hurst The Electricity Act 1989 and the Acquisition of Land Act 1981

Notice ID: SUT1217154

Notice effective from
26th June 2019 to 26th July 2019

THE NATIONAL GRID ELECTRICITY TRANSMISSION PLC (LONDON POWER TUNNELS 2) (CIRCUIT 2 - NEW CROSS TO HURST) COMPULSORY PURCHASE ORDER 2019 Compulsory Purchase of Land and New Rights in Land at New Cross to Hurst The Electricity Act 1989 and the Acquisition of Land Act 1981

Notice is hereby given that NATIONAL GRID ELECTRICITY TRANSMISSION PLC (Company Registration Number 02366977) has made The National Grid Electricity Transmission PLC (London Power Tunnels 2) (Circuit 2 - New Cross to Hurst) Compulsory Purchase Order 2019 (in this Notice referred to as "the Order"), under Section 10 and Schedule 3 to the Electricity Act 1989. It is about to submit the Order to the Secretary of State for Business Energy and Industrial Strategy for confirmation, and if confirmed, the Order will authorise National Grid Electricity Transmission PLC to purchase compulsorily the land and the new rights over land described below for the purposes of an underground tunnel and electricity cables from a substation east of Sandgate Street, Southwark ("the New Cross Substation"), to a substation off Stable Lane, Bexley ("the Hurst Substation"), via sites with access shafts and headhouses south of Nelson Mandela Road, Greenwich, and east of Eltham Grid Substation, south of Falconwood Field, Greenwich, together with related works to facilitate the transmission of electricity within and across London.

A copy of the Order and of the accompanying map may be found online at

www.londonpowertunnels

.

co.uk

and seen at all reasonable hours at the offices of National Grid Electricity Transmission PLC at 1-3 Strand, London, WC2N 5EH and at the following locations:

Depository Location

Address

Camberwell Library

48 Camberwell Green, Camberwell, London SE5 7AL

Peckham Library

122 Peckham Hill St, Peckham, London SE15 5JR

West Greenwich Library

146 Greenwich High Rd, Greenwich, London SE10 8NN

Eltham Library

Archery Rd, Eltham, London SE9 1 HA

Bexley Community Library

Bourne Rd, Bexley DA5 1LU

Any objection to the Order must be made in writing to the Secretary of State for Business, Energy & Industrial Strategy at 1 Victoria Street, London SW1H 0ET before 2 August 2019 and should state the title of the Order, the grounds of the objection and the objector's address and interests in the land. DESCRIPTION OF LAND AND THE NEW RIGHTS LAND:

Land to the south of Nelson Mandela Road, Greenwich for a headhouse site and shaft and land east of the Eltham Grid Substation, south of Falconwood Field, Greenwich for a headhouse site and shaft. NEW RIGHTS:

Rights associated with the construction and operation of a tunnel and electricity cables project. These rights cover the rights required for all construction related activity associated with the project, including (but not limited to) access, all construction-related activities, laying and moving services, airspace rights and fencing and hoarding. There are also rights for access during the operational phase in locations where there is to be an above ground installation.

These rights are labelled as "Construction Compound Rights", "Construction Access Rights", "Operational Access Rights" and "Tunnel and Cable Rights" in the Order and Schedule, each of which is defined in detail at paragraph 6 of the Order. Gareth Burden

Senior Project Manager - London Power Tunnels 2 National Grid Electricity Transmission PLC Dated: 13 June 2019

Attachments

SUT1217154.pdf Download

Comments


or Register to leave a comment and/or receive comment alerts.

Related notices